This week the JEMS team have been working a maintenance job at Weisman Dairies in Somerset. With an ETP which is around 7 years old. The aeration pattern in the aeration lanes had become irregular and insufficient. This was starting to affect the final effluent clarity. The decision was taken to replace the aeration grid fine bubble air diffusers.

JEMS were drafted in as a sub-contractor, providing a 4 man team to carry out the task. Working in a confined space environment, the job was carried out safely, efficiently and to a high standard. Both (400mᵌ) aeration lanes were completed in under 2 weeks.

With a very happy client (having finished ahead of schedule). This was another successful job carried out by JEMS Environmental.